The sequence gave each flight a job. Apollo 9 was planned to conduct the first crewed lunar module test in Earth orbit, while Apollo 10 was to test the module in lunar orbit as a landing rehearsal. For a program working toward a deadline, that division made the equipment and its operation the immediate focus before the landing attempt. [S1]

Apollo 9's planned spacewalk was designed to test the spacesuit and portable life-support system and demonstrate an outside route between spacecraft if the internal tunnel or hatches had a problem. Crews and backups trained in simulators and for the spacewalk, according to NASA. [S1]

Preparation ran in parallel at NASA's Kennedy Space Center in Florida. Workers stacked the Apollo 10 spacecraft on its Saturn V rocket on February 6, 1969, and engineers began integrated tests ahead of a planned mid-March rollout. Meanwhile, on February 10, engineers tested docking between Apollo 11's command and lunar modules; five days later they joined the lunar module's ascent and descent stages for further testing. [S1]

NASA also built a containment step into the return plan. Its Lunar Receiving Laboratory was designed to isolate returning astronauts, spacecraft and lunar samples against possible lunar microorganisms while keeping samples as pristine as possible. On February 6, three test subjects successfully completed a test of the mobile quarantine facility's emergency oxygen supply under simulated aircraft pressure loss. [S1]

Source documents

  1. 55 Years Ago: Five Months Until the Moon Landinghttps://www.nasa.gov/history/55-years-ago-five-months-until-the-moon-landing/