NASA selected the south Mississippi site after presentations and evaluations; Marshall Flight Center in Alabama and Edwards Air Force Base in California had also sought the assignment. Before testing could begin, Stennis had to convert stands built for rocket-stage tests to support single-engine hot fires. [S1]
The equipment had to do more than hold an engine. Stennis installed and calibrated propellant tanks, developed thrust measurement and added a way to pivot engines on the Fred Haise Test Stand. A diffuser on the A-2 stand allowed testing at simulated altitudes up to 60,000 feet. [S1]
For a full-duration, 500-second hot fire, the stand's run tanks alone were too small. Teams therefore transferred cryogenic propellants in real time from barges to the tanks and on to the engine, requiring precise measurement and flow control. [S1]
From May 1975 through July 2009, Stennis conducted 3,244 shuttle main-engine tests, accumulating more than 820,000 seconds of hot fire. NASA says the work expanded the site's propulsion-testing capabilities and helped open the door to commercial aerospace test projects. That is a practical example of a public testing assignment creating capabilities with later commercial uses. [S1]
Source documents
- A Defining Era: NASA Stennis and Space Shuttle Main Engine Testinghttps://www.nasa.gov/centers-and-facilities/stennis/a-defining-era-ssme/